A date in a contract without a start trigger is a wish. The clock only starts when three documents exist.
25–35 days after sample sign-off. That runs from sample sign-off, not from order date, and not from deposit. If the sample approval takes three weeks, the delivery moves three weeks.
So the contract needs both dates: order date and the date the sample was approved. Everything between them is the client's scope.
Drawing approval, sample approval, production start, pre-shipment inspection, shipment, arrival. Six dates, each with an owner.
The ones that slip are drawing approval and cover availability. Both are client-side in most projects and neither is usually scheduled.
Liquidated damages are normal on fit-out contracts and rare on furniture. More useful clause: a weekly progress report with photographs from the workshop, starting at production.
Then a shipment split clause — if the date is at risk, the order ships in two parts with the critical items first.
The only honest way to pull a date in is to split the order into two shipments. Nothing moves a 25-day production run to 12 days without changing something about the product.
Schedule planning sits in the lead time guide, and the delay causes in what delays a container.