This guide breaks the date down, then covers sampling, packing and the part of the calendar that has nothing to do with the factory.
Drawing and PO confirmation 3–5 days. Timber release and cutting 5–7 days. Machining and frame assembly 7–10 days. Upholstery 5–8 days. Finishing and cure 3–5 days. QC and packing 2–3 days.
Add them up and the total is 25–35 days after sample sign-off. The steps run partly in parallel — upholstery starts as frames come off assembly — which is why the sum is shorter than the individual numbers suggest.
7–10 days for a frame sample, 12–15 with cover and finish. Sampling runs on an existing frame where the shape allows, which is why a sample in a new cover is quick and a sample in a new shape is not.
Sign off the sample in writing, with photographs from four angles and the cover roll number attached. Every later batch is checked against that record, not against a memory of a meeting.
Drying, covers and finishing, in that order. Drying has invisible slack, so it is where a rush date comes from — see moisture content at packing for what that costs later. Covers slip when the mill runs out of a colour and the substitute has a different roll. Finishing slips when humidity will not let a lacquer cure.
The only honest way to pull a date in is to split the order into two shipments. Splitting an order does not shorten the work; it shortens the wait for the first half.
0.11–0.15 m³ per dining chair in a carton, so about 450–550 per 40hq — 68 m³ usable, 28 t limit. Booth runs ship knocked down, booth runs ship knocked down; a 3 m run is 1.1–1.4 m³.
Marking matters as much as the packing. Cartons marked to the floor or room block let the site sort before unpacking, which is the difference between a two-day and a two-week install — the detail is in packing by room block.
Production is 25 to 35 days. Freight is not. Sea freight from Foshan to a European port runs roughly 30 to 45 days door to door depending on routing, and the booking has to be made two to three weeks before the cargo is ready.
Which means the number that matters for a fit-out is the arrival date, not the production date. Work backwards from the install, not forwards from the order.
Send it over. We will mark the joints, the species by part and the sizes that need confirming.