Where the 25 to 35 Days Actually Go

We quote 25–35 days after sample sign-off. Buyers hear one number; the workshop sees six steps, and only one of them has anything that could be called slack.

This guide breaks the date down, then covers sampling, packing and the part of the calendar that has nothing to do with the factory.

The six steps

Drawing and PO confirmation 3–5 days. Timber release and cutting 5–7 days. Machining and frame assembly 7–10 days. Upholstery 5–8 days. Finishing and cure 3–5 days. QC and packing 2–3 days.

Add them up and the total is 25–35 days after sample sign-off. The steps run partly in parallel — upholstery starts as frames come off assembly — which is why the sum is shorter than the individual numbers suggest.

Sampling comes first

7–10 days for a frame sample, 12–15 with cover and finish. Sampling runs on an existing frame where the shape allows, which is why a sample in a new cover is quick and a sample in a new shape is not.

Sign off the sample in writing, with photographs from four angles and the cover roll number attached. Every later batch is checked against that record, not against a memory of a meeting.

Where the date slips

Drying, covers and finishing, in that order. Drying has invisible slack, so it is where a rush date comes from — see moisture content at packing for what that costs later. Covers slip when the mill runs out of a colour and the substitute has a different roll. Finishing slips when humidity will not let a lacquer cure.

The only honest way to pull a date in is to split the order into two shipments. Splitting an order does not shorten the work; it shortens the wait for the first half.

Packing and the container

0.11–0.15 m³ per dining chair in a carton, so about 450–550 per 40hq — 68 m³ usable, 28 t limit. Booth runs ship knocked down, booth runs ship knocked down; a 3 m run is 1.1–1.4 m³.

Marking matters as much as the packing. Cartons marked to the floor or room block let the site sort before unpacking, which is the difference between a two-day and a two-week install — the detail is in packing by room block.

What is not in the date

Production is 25 to 35 days. Freight is not. Sea freight from Foshan to a European port runs roughly 30 to 45 days door to door depending on routing, and the booking has to be made two to three weeks before the cargo is ready.

Which means the number that matters for a fit-out is the arrival date, not the production date. Work backwards from the install, not forwards from the order.

Notes in this guide

24 Nov 2026·Lead Time
How Long a Sample Really Takes
Seven to fifteen days, and the difference is whether the shape already exists.
24 Nov 2026·Lead Time
Five Things That Hold a Container
Production finishes on time and the container still misses the vessel. These are the five reasons, in order of frequency.
24 Nov 2026·Lead Time
Packing an Order With Fourteen Models
Mixed orders are packed by destination, not by product. Get that wrong and the site unpacks fourteen piles to build one room.
24 Nov 2026·Lead Time
Incoterms on a Furniture Order, Plainly
EXW, FOB, CIF, DDP. Four letters that decide who owns the risk at each point, and which one a hotel project should use.
24 Nov 2026·Lead Time
What a Rush Order Can and Cannot Shorten
Machining can be doubled with a second shift. Drying cannot. That is the whole answer.
24 Nov 2026·Lead Time
Planning Around the Spring Festival
Four weeks of shutdown and two weeks of slow restart. Orders placed in January arrives in April.
24 Nov 2026·Lead Time
What a Pre-Shipment Inspection Should Cover
Ninety minutes, five checks, and a report with photographs. Without it, the first time anyone sees the chairs is on site.
24 Nov 2026·Lead Time
Loading a 40HQ Without Wasting a Cubic Metre
Sixty-eight cubic metres, packed by hand in six hours. The plan decides whether the last twenty chairs fit.
24 Nov 2026·Lead Time
Set the Install Date, Then Work Backwards
Opening dates do not move. Production dates do. Only one of them is worth planning from.
24 Nov 2026·Lead Time
Volume Weight and Why Chairs Cost What They Do to Ship
Furniture ships by volume, not by weight. That is why a light chair and a heavy one cost the same to move.
24 Nov 2026·Lead Time
How Long a Repeat Order Really Takes
Repeat orders skip sampling and skip nothing else. The saving is two weeks, not two months.
24 Nov 2026·Lead Time
Booking a Production Slot, Not Just Placing an Order
The order is confirmed and the workshop is full for three weeks. The lead time clock starts when the line is booked, not when the deposit lands.
24 Nov 2026·Lead Time
Material Lead Times: Timber, Cover and Foam
Production is 25 days. Getting the cover in the right colour can take 40. Material is what actually decides the date.
24 Nov 2026·Lead Time
The Sample Room Queue Nobody Warns You About
Sample rooms are small and everyone wants samples in the same month. The queue is why a two-week sample takes five.
24 Nov 2026·Lead Time
Deposit Timing and When Materials Actually Get Released
The deposit clears on Friday and the timber is released on Monday. Between those two dates sits a purchase order nobody sent.
24 Nov 2026·Lead Time
When the Cover Is Late: Four Options and Their Costs
Frames are finished and the cover arrives in three weeks. Four ways out, and only one of them protects the delivery date.
24 Nov 2026·Lead Time
FCL or LCL: The Break-Even for Furniture
Furniture is bulky and light, which is the worst combination for LCL. The break-even sits lower than most buyers expect.
24 Nov 2026·Lead Time
Consolidating Three Suppliers Into One Container
Three factories, one container, one departure. The maths works until one supplier is three days late.
24 Nov 2026·Lead Time
Sailing Schedules and Port Congestion
The quoted transit time is port to port and the container sits at anchor for six days. That six days is not in the schedule.
24 Nov 2026·Lead Time
Documents for Clearance: The List That Stops a Container
Customs does not hold cargo for the goods. It holds them for a missing certificate, and the container waits at your cost.
24 Nov 2026·Lead Time
Delivery Day: The Checklist That Saves a Week
Truck arrives, nobody knows where the goods go, and 200 cartons sit in a corridor. Two hours of planning prevents that.
24 Nov 2026·Lead Time
Site Readiness: Nine Things That Must Be True
Furniture arriving into a wet building is furniture stored in a humid room. Site readiness is a condition of delivery, not a courtesy.
24 Nov 2026·Lead Time
Installation Labour: How Many People for 200 Chairs
Two people can install 200 chairs in a day if the cartons are sorted by room. Four people take two days if they are not.
24 Nov 2026·Lead Time
Cartons, Foam and Pallets: The Waste Nobody Budgets
Two hundred chairs arrive in 200 cartons with foam, plastic and pallets. Getting that off site is a cost line, not a detail.
24 Nov 2026·Lead Time
The Punch-List Week: What Gets Fixed and What Gets Deferred
Forty items on the list, five days before opening. Sorting them by what guests see is the only way through.
24 Nov 2026·Lead Time
Seasonal Capacity in Foshan: The Year in Four Quarters
Everything is possible in June and nothing is possible in December. The workshop calendar decides more dates than the quotation does.
24 Nov 2026·Lead Time
Reading a Production Report: Four Numbers That Tell the Truth
Progress reports say 'on schedule' until the day they do not. Four numbers turn the sentence into evidence.
24 Nov 2026·Lead Time
Air Freight: When It Is Cheaper Than Waiting
Air freight costs eight to twelve times sea. It still pays for itself on parts, samples and any delay that would move an opening date.
24 Nov 2026·Lead Time
Free Time, Demurrage and the Bill Nobody Expects
The container arrives, the site is not ready, and the port charges per day. Free time is a number on the booking that decides the cost.
25 Nov 2026·Lead Time
Six Models in One Order: What the Model Count Does to the Calendar
One model at 600 pieces and six models at 100 pieces are the same number of chairs. The second order takes eight to eleven working days longer, and none of it is cutting.
14 Oct 2026·Lead Time
Packing by Room Block: How a 120-Key Delivery Stays Sorted
Furniture for a hotel under fit-out does not fail at the factory. It fails on the loading bay, when 120 identical rooms arrive as one unmarked pile.