Site Readiness: Nine Things That Must Be True

Furniture arriving into a wet building is furniture stored in a humid room. Site readiness is a condition of delivery, not a courtesy.

Part of the lead time guide — Where the 25 to 35 Days Actually Go

The building

Wet trades finished, screed dry, plaster dry, glazing in. Then the room can accept furniture without becoming its drying room.

Heating and ventilation running, or a dehumidifier in place. The new building releases hundreds of litres of water in its first weeks.

The access

Route clear and protected, lift available and booked, doors hung with the furniture able to pass. The door frame fitted after delivery is a door frame that gets removed.

Site power available for tools, and a secure lock-up area.

The people

Nominated receiving contact, a signature authority, and someone from housekeeping on site at first unpacking. Three names, exchanged a week before delivery.

Without them, cartons get signed for by a subcontractor who leaves the site that afternoon.

What to do when the site is not ready

Delay the delivery. Furniture stored on an unfinished site takes damage, and the damage is nobody's fault in the paperwork but yours in the budget.

The container crossing the tropics can push 8% timber to 13% and back; starting at 8–10% leaves room for the round trip. Storage conditions sit in storage on site before install, and the delivery checklist in delivery day checklist.