Mixed orders are packed by destination, not by product. Get that wrong and the site unpacks fourteen piles to build one room.
By model: all Q101 in one block of cartons, all Q108 in the next. Efficient at the factory, painful on site.
By room or floor: each carton holds what one room needs. Slightly less efficient at the factory, and the difference between a two-day and a two-week install.
Carton stencil: project, block, room type, model, quantity, and a sequence number. Then the packing list on the outside of the first carton of each block.
Anything unmarked gets opened twice and counted three times.
0.11–0.15 m³ per dining chair in a carton, so about 450–550 per 40hq — 68 m³ usable, 28 t limit. Mixed orders lose 5–8% of volume to odd-shaped gaps, which is the difference between fitting and not fitting.
Plan the load, don't hope. The loading plan is a page of rectangles and it takes an hour.
Photographs of the packed container, the packing list, and the carton marking template.
Three items that let you check the install plan before the vessel sails. More on the sequence in the lead-time guide, and the site side in packing by room block.