Machining can be doubled with a second shift. Drying cannot. That is the whole answer.
Machining and assembly: yes, with a second shift, at a premium. Upholstery: partly, if the covers arrive on time. Packing: yes, with more hands.
Together those are 7–10 days and 5–8 days of the schedule, so compressing them can save a week.
Drying. 5–7 days of kiln time is physics, not staffing. Pull it and the frames move in service, which is a cost paid eighteen months later.
Finishing needs cure time. Skip it and the lacquer stays soft and takes a print from the packing carton.
The only honest way to pull a date in is to split the order into two shipments. Ship the first rooms complete and the rest three weeks later, so the install can start.
Or buy from stock, if the model is a stocked one. That is the only way to a date under 25–35 days without touching the drying schedule.
"Which step are you shortening?" If the answer is anything other than machining or packing, the date is being bought from the frame.
The steps are listed in the lead-time guide, and the drying argument in moisture content at packing.
Send the floor plan and the seat count. Quote and finish chip in one reply.
Start a conversation →