Two weeks in a humid plant room undoes a month of careful packing. The storage plan belongs in the contract, next to the delivery date.
Humidity. New buildings are wet. Concrete, plaster and screed release water for weeks. Chairs stored in that environment take on moisture through the cartons and the frames swell at the joints.
Load. Cartons stacked above the specified height crush the bottom layer. Chair frames take vertical load well, cartons do not.
Heat. Plant rooms at 35 °C with a boiler are kilns. Lacquer softens, PU leather can delaminate, and glue lines creep under load.
Dry, ventilated, off the floor on pallets, out of direct sun, cartons closed. Temperature between 15 and 25 °C and humidity under 65%. If the building has no such room, keep the stock in the container or in a rented unit until two weeks before installation.
Stack height: three cartons for chairs, two for tables. Anything above that goes on racking, not on the stack.
Unpack two weeks before install if the room is at service humidity. Chairs equalise in the room they will live in, and any movement happens before the guests arrive rather than after.
Do not unpack into a room that is still being plastered. Timber at 8–10% at packing in a room at 80% relative humidity gains three points in a week, and the first thing that shows is a tight tenon pushing a shoulder line.
Count against the packing list before the cartons go into storage, not after. Shortages found three weeks later are a shipment, not a claim.
Then photograph the storage conditions — the room, the pallets, the stack height. If something does go wrong, the photograph is the difference between a manufacturing claim and a site handling one. Packing and delivery sequencing sit in the lead time guide, and install date backwards plans the sequence.