Opening dates do not move. Production dates do. Only one of them is worth planning from.
Install date, minus snag week, minus freight, minus production, minus sampling, minus approval. Working forwards from a PO gives a date that arrives after the opening.
Roughly: 4–5 months from approval to install on a sea shipment.
Approval takes three rounds instead of one. Freight is booked late. The room is not ready when the container lands and the furniture goes into storage — which costs money and delays the snag list into the opening week.
Freeze the layout and the finish early. Everything downstream — sampling, cover, production — is faster when those two are settled.
Then book freight at PO, not at completion. That single habit removes two weeks from most projects.
25–35 days after sample sign-off for production, 30–45 days for freight, one week for install and snag. That is the spine of the plan.
The steps are in the lead-time guide, and the room-side sequence in the restaurant setup guide.