This is the sequence we see work, and the four points where it usually breaks.
Layout freeze. Seat count fixed per room. FF&E list with quantities. Budget per seat. Then samples, then the PO.
Layout has to freeze before the chair is chosen, because the chair determines the count and the count determines the budget. Rooms designed around a chair that arrives 30 mm wider than the drawing have to lose seats.
A seat costs the chair plus its share of tables, banquettes and circulation. One hundred and twenty seats along a banquette wall cost less per seat than the same count in loose chairs, because the banquette carries the space.
Working backwards from the room budget is more reliable than forwards from a chair price. Production is 25–35 days after sample sign-off, freight is 30–45 days on top, so the furniture order sits about three months before the install date.
Covers, every time. Mills run out of a colour, the substitute has a different roll, and the batch does not match the sample. Choose from stocked ranges if the opening date is fixed.
Banquettes arrive late when the wall is not finished, because the run is measured against the finished wall. Plaster and skirting eat 30–60 mm. Measure after the wall, not before.
Chairs before banquettes. Banquettes before tables, because the table position depends on the seat depth. Then the snag list, which runs one to two weeks on a 120-seat room.
Keep 3–5% spares on site, not in a warehouse. Chairs damaged in the first service should be replaced the same week, not ordered.
Layout not frozen before the chair was chosen. Cover chosen from a swatch that was not a stock range. Banquette measured before the wall was finished. Spares counted as zero.
Each of those is a week or more, and all four are decisions rather than accidents.