Furniture installs last and gets blamed for the delay. The fix is a schedule where furniture is a trade, not a delivery.
Ceiling, walls, floor, joinery, fixed furniture, services commissioning, loose furniture, snag. Fixed furniture before loose, always.
Banquettes and wall benches are fixed furniture. They need the wall finished and the floor laid, and they block the room for everything after them.
Wet trades not finished. Skirting not fitted. Power points not commissioned. Any of those and the cartons sit in a corridor for a week.
Each is a two-day slip that becomes a two-week storage problem.
The fortnightly site meeting with furniture on the agenda as a trade line, with a date and a dependency. Not a delivery note.
Then a site walk one week before delivery with the main contractor, checking the nine readiness items.
One coordinator, from the client side, with authority over all three parties. Without one, the list circulates and nobody closes lines.
Readiness items sit in site readiness before delivery, and the snag process in punch list week.