Receiving Furniture While the Site Is Still Working

A partial handover means delivering into a building with other trades in it. That is a protection problem before it is a logistics one.

Part of the opening guide — Furniture for a Hotel Restaurant, in the Right Order

Protect the route first

Floor protection along the whole route, corner guards on door frames, and a covered lift. Ten minutes of laying protection saves a floor claim.

Then a written route agreement with the main contractor, because the route changes when another trade needs it.

Staging area

The lockable room for cartons, dry, with the door wide enough for a pallet. Chairs staged there and moved to the room in the final week, not stored in the room while other trades work.

The container crossing the tropics can push 8% timber to 13% and back; starting at 8–10% leaves room for the round trip. The wet building is a humid store.

Who signs

The nominated receiver with authority, present for every delivery. Not a subcontractor who leaves at four.

Count and photograph before signing, and record any damaged carton with the label in frame.

When to refuse a delivery

When the room is not weathertight, or the floor is not finished and the furniture would have to be moved twice. Refusing costs a re-delivery; accepting costs a claim.

Delivery checks sit in delivery day checklist, and storage in storage on site before install.