Opening a Dining Room: The Furniture Timeline

From measured survey to opening night is nine months for furniture. Six of those months are before anything is ordered.

Part of the opening guide — Furniture for a Hotel Restaurant, in the Right Order

The nine months

Survey and test fit: month one. Specification and sampling: months two to four. Approval: month five. Production and shipping: months six to eight. Install and snag: month nine.

25–35 days after sample sign-off is production. The ship adds five to six weeks, and the buffer adds another.

Where projects lose time

Sampling. Three revisions on a cover take six weeks nobody scheduled. Approval on a finish chip can take a month if the client's designer is on another project.

Then the floor plan changes after the order, which resets the table mix.

Working backwards

Fix the opening date, then subtract: 8 weeks install and snag, 6 weeks shipping, 5 weeks production, 4 weeks sampling, 2 weeks specification. That is 25 weeks minimum before the order.

Anything less and the schedule depends on everything going right, which it will not.

The three dates to protect

Sample approval, production slot, and vessel booking. Each one missed moves the opening date, and each one is a document rather than an intention.

Detailed scheduling sits in install date backwards, and sampling in the lead time guide.