Repeat orders skip sampling and skip nothing else. The saving is two weeks, not two months.
25–35 days after sample sign-off. On a repeat with no changes, the drawing and sample stages collapse and production starts on the purchase order.
That removes 7–10 days for a frame sample, 12–15 with cover and finish from the front of the schedule and leaves the 25–35 days of production. Two weeks saved, sometimes three.
Cover availability. The roll from the first order is gone and the new roll is a different dye lot, so the buyer spends a week deciding whether that matters.
Also: a supplier who no longer runs that model, a hardware item discontinued, and timber that arrived at a different moisture content and needs longer in the kiln.
Keep the drawing, the sample and the finish reference together, and record the cover roll number on the original order. Then a repeat is a purchase order with three attachments.
Ask at the first order what the minimum production slot is. 6 pcs per line is the order minimum; the slot minimum may be higher during peak season.
Order four months before the opening date for a repeat, six for a first order. Then check the production calendar for the New Year shutdown before fixing the date.
Seasonal capacity sits in seasonal capacity in Foshan, and the general schedule in the lead time guide.
Send the floor plan and the seat count. Quote and finish chip in one reply.