The order is confirmed and the workshop is full for three weeks. The lead time clock starts when the line is booked, not when the deposit lands.
Timber machining, metal shop, upholstery, finishing, packing. Each line has a daily output, and a slot is a block of days reserved for one order on those lines.
The 400-chair order takes two weeks on the frame line and one on upholstery. If the upholstery line is booked by a bigger order, the frames wait — that is where the extra three weeks come from.
At deposit, before the cover is confirmed. The slot is the constraint; the cover is a detail that can arrive during production of the frames.
Then get the slot dates in writing: frame start, upholstery start, packing. Three dates answer the whole question.
Two to three months before Chinese New Year, every line is full and everyone wants delivery before the shutdown. Ordering into that window adds two to three weeks to any quoted lead time.
Booking a slot in October for a January shipment is normal practice, not early planning.
Which line, which dates, and what happens if the deposit slips a week. The supplier who cannot answer the third question has not booked anything.
Calendar detail sits in Chinese New Year and the production calendar, and the overall sequence in the lead time guide.