Four weeks of shutdown and two weeks of slow restart. Orders placed in January arrives in April.
Spring Festival falls in late January or February and the workshop closes for two to four weeks. Before the break, everyone ships; after it, the workforce returns in stages.
Effectively, December to March is a five-month window for three months of work.
Place orders before mid-November for anything that has to be installed in Q1. After that, expect the date to move by three to four weeks.
For orders placed in January, book the vessel at the same time as the PO rather than after production.
Workers travel home and come back over two weeks. Sub-suppliers — foam, powder, cartons — restart at different times, so a workshop can be open and still waiting for a component.
Which is why the second half of February is not a normal production month, whatever the calendar says.
Work backwards from the install. Production 25–35 days after sample sign-off, freight 30–45 days, plus the festival if it lands in the window.
Four to five months from PO to install is a safe number for a Chinese furniture order. The steps are in the lead-time guide, and the freight side in five things that hold a container.