The quoted transit time is port to port and the container sits at anchor for six days. That six days is not in the schedule.
Booking cut-off, container gate-in, vessel loading, and any waiting at the destination port. Then customs clearance and inland transport.
Door to door on a 25-day transit is realistically 40–50 days, and that is without congestion.
Chinese New Year and the weeks before it. European summer port staffing. US west coast labour disputes. Each adds days to weeks and none of them appear in a quotation.
Booking two weeks early is the only reliable hedge, and it costs nothing.
Ask for the vessel name, the sailing date and the estimated arrival, not just a transit time. Then track the vessel — a rolled booking shows up as a container that never gated in.
The supplier who cannot name the vessel two weeks before sailing has not booked space.
Six weeks between arrival and installation. That absorbs a port delay, a customs query and a short-landed carton without moving the opening date.
Install sequencing sits in install date backwards, and clearance documents in documents for clearance.