Loading a 40HQ Without Wasting a Cubic Metre

Sixty-eight cubic metres, packed by hand in six hours. The plan decides whether the last twenty chairs fit.

Part of the lead time guide — Where the 25 to 35 Days Actually Go

The numbers

68 m³ usable, 28 t limit. Chairs at 0.11–0.15 m³ per chair in a carton; stools at 0.09–0.12 m³.

Booth runs knocked down at a 3 m run is 1.1–1.4 m³. Tables at 0.25–0.35 m³.

How a mixed load is planned

Heavy and rigid at the floor and the front, cartons on top, gaps filled with small items. Anything that can crush goes last.

The plan is a side elevation and a plan view, drawn to scale. One page, and it is the difference between a 92% load and a 78% load.

What ruins a load

Packing cartons to a nominal size and finding they bulge. Cartons that are 10 mm oversize cost 5% of the container across 400 units.

Untaped carton seams let in humidity on a 40-day voyage, which is what turns a carton corner soft.

The last twenty chairs

They go in because the plan reserved space for them. Without a plan, the crew loads until the door will not close and the remainder ships next month.

Volume maths is in the lead-time guide; the marking side in packing an order with fourteen models.