Material Lead Times: Timber, Cover and Foam

Production is 25 days. Getting the cover in the right colour can take 40. Material is what actually decides the date.

Part of the lead time guide — Where the 25 to 35 Days Actually Go

Timber

Standard species are in stock at the mill or two weeks away. White oak in a specific grade and thickness is four to six weeks if it is not on the rack.

Then it has to dry. Kiln time is not compressible — a rush order in green timber is a rush order that cracks in the container.

Cover

Stock covers ship in a week. The custom colour or a mill order is four to six weeks, and a custom weave is eight.

That is the single most common reason a chair order slips. The frame is ready and the cover arrives after the planned upholstery slot.

Foam and hardware

Standard foam densities are stock. The moulded shape is a tooling lead time of three to four weeks before the first pad.

Hardware: glides, inserts, brackets — usually stock, but a specific insert or a branded glide can be four weeks. That is why the hardware schedule matters at order stage.

How to plan around it

Confirm cover availability before fixing the delivery date, and tooling before confirming the sample. Two checks, both a week, both remove the main sources of slip.

Delay causes sit in what delays a container, and cover ordering in what happens when a cover is late.