When the Cover Is Late: Four Options and Their Costs

Frames are finished and the cover arrives in three weeks. Four ways out, and only one of them protects the delivery date.

Part of the lead time guide — Where the 25 to 35 Days Actually Go

Option one: wait

Hold the frames and upholster when the cover arrives. Costs nothing in materials, and moves the delivery date by the cover delay.

That is the right answer when the install date has slack. It is the wrong answer when the room opens in three weeks.

Option two: split the shipment

Ship the frames or the finished chairs in a first container and the rest later. Preserves part of the installation programme and doubles the freight cost on the split items.

Works best when the late cover is on one model and the room can open with the others installed.

Option three: substitute cover

The stock cover in a similar colour and grade. Protects the date and creates a colour difference that will be visible in the room.

Acceptable for back-of-house and storage areas, and a mistake in a dining room where guests see the row.

Option four: air freight the cover

Air freight on 200 m of cover costs a few hundred dollars and buys two weeks. That is usually the cheapest fix on the list, and it is the one nobody thinks of.

Air freight economics sit in air freight when it makes sense, and cover lead times in material lead times.