How Long a Sample Really Takes

Seven to fifteen days, and the difference is whether the shape already exists.

Part of the lead time guide — Where the 25 to 35 Days Actually Go

Two kinds of sample

Sample on an existing frame in a new cover: 7–10 days for a frame sample. The frame is already jigged, the only new work is the cover and the finish.

Sample in a new shape: the drawing goes to the sample room, a jig gets built, and the first frame is cut by hand. That is 12–15 days before anything is upholstered.

What slows it down

Waiting for the cover. If the fabric ships from Europe, the sample room sits idle for three weeks and the 15-day figure becomes 40.

Waiting for a decision. One sample approved with three comments restarts the clock on the parts that changed, and that is where most projects lose a fortnight.

How to shorten it

Send the cover to the factory, not to the hotel. Have the finish chip approved before the sample is built, not after.

Approve in one round. Collect every comment into one list, decide, then send it once.

What the sample has to prove

Joinery, dimensions, comfort, cover and finish. Five things, and none of them can be judged from a photograph.

Sign it with a date, keep one copy at the factory and photograph it from four angles. The sequence is in the lead-time guide, and the approval record in what goes in a sample approval record.