Six Models in One Order: What the Model Count Does to the Calendar

One model at 600 pieces and six models at 100 pieces are the same number of chairs. The second order takes eight to eleven working days longer, and none of it is cutting.

Part of the lead time guide — Where the 25 to 35 Days Actually Go

The baseline run

The single-model run of 600 side chairs takes 23 working days on our floor: 4 days cutting and machining, 5 days joinery and assembly, 3 days sanding, 4 days finishing and 5 days upholstery, with packing overlapping the last two stages.

Nothing in that sequence is optimistic. Ask the same question per model on a six-model order and the answer usually comes back identical, which is where a delivery date quietly goes wrong. Six models at 100 pieces also sit under the quantity where the per-chair price flattens, so the model count is paid for twice: once in working days and once in the unit price.

Changeover is paid per model

Colour changes cost four hours each on a spray line: booth clean, gun change, first-off check against the approved chip. Six models in four colours take 12 hours of that, or a day and a half, that no chair absorbs.

Upholstery changeover runs 2 to 3 hours per model for a new roll, a new cutting pattern and a new thread. Six models is 15 hours. Packing adds 2 hours per model because the carton size and the label change with the frame, so a six-model order carries roughly 27 hours of pure switchover before tooling is counted at all.

Tooling sits in front of the first cut

New shapes need jigs before the line starts, and tooling is 3 to 4 days per shape in our workshop. Three new shapes in one order push the first cut back 10 to 12 working days, and that delay lands ahead of the schedule rather than inside it, which is why it is missed.

Reusing an existing frame with a different cover and finish removes it: no new jigs, and the only added time is the switchover. That trade is set out in production slots and booking.

Grouping that buys days back

Sequence by finish family rather than by model number. Four models in one colour run back to back take one 4-hour colour change instead of four. Same logic on covers: three models in one fabric need one roll change, not three.

Write the line order on the purchase order and let the factory schedule inside it. Left alone, the line follows whatever cartons packing needs that week, and the changeover cost comes back as a date rather than an invoice.

What to put in the contract

Ask for a calendar that treats model count as an input: days per model for changeover, days of tooling, and the sequence the factory intends to run. Budget 23 working days for the first model and about 1.5 days for each additional one on a small order, which puts six models at 30 to 34.

Repeating an existing model skips tooling, and the timing is covered in how long a repeat order takes. The full set of stages, including the ones that move, is in the lead-time guide, and the frames that share tooling across models are listed under hotel dining chairs.