Sample rooms are small and everyone wants samples in the same month. The queue is why a two-week sample takes five.
9 in the sample room. Nine people make every sample, and they also make the first article for new production runs.
In September and October, every hotel project wants a sample before the winter design freeze. The queue goes from three days to three weeks.
7–10 days for a frame sample, 12–15 with cover and finish. That is bench time, not calendar time. Add the queue, the courier and the approval round trip and a sample is realistically four weeks door to door.
Two revisions and it is eight.
Pay for the sample at order intent rather than at order. Suppliers prioritise work that is already funded, and a deposit on the sample is the cheapest queue jump available.
Then limit the brief: one chair, one cover, one finish. Samples that arrive with three options take three times as long.
Sample approval four months before opening, production order three months, delivery six weeks before install. That sequence has no slack, which is why projects that start late always feel late.
Sampling sequence sits in sampling timeline, and the cost of samples in what a sample really costs.