Three factories, one container, one departure. The maths works until one supplier is three days late.
Each supplier delivers to a consolidation warehouse near the port. Goods are held, inspected and loaded together, then the container is sealed and shipped.
Cost saving is real: one container instead of three LCL bookings, and one set of documents.
One supplier's three-day delay holds the whole container. Then the warehouse charges storage from day three and the sailing is missed.
Which is why consolidation needs a stated cut-off date and a rule for late arrivals — ship without them, or wait and pay.
Goods get restacked and the cartons that travelled well from one factory get crushed at the consolidation point. Photograph on arrival at the warehouse, not at the port.
Then insist the original cartons are not opened for inspection unless the inspector reseals them.
When the combined volume is over 40 m³ and each supplier ships more than 10 m³. Below that, the handling cost eats the freight saving.
Loading sequence sits in container loading plan, and the port side in shipping schedule and port congestion.