Two people can install 200 chairs in a day if the cartons are sorted by room. Four people take two days if they are not.
Finished chairs: 40–50 per person per day including unpacking, positioning and waste removal. Tables: 15–20 per person per day, because levelling takes time.
So 200 chairs and 40 tables is four people for two days, with a fifth for waste and floor protection.
Cartons sorted by model instead of room. Lifts out of service. Floors not finished so furniture has to move twice. Missing glides, which stops a whole row.
Each of those is a planning failure, not a labour shortage.
Fixed seating first, then tables, then chairs, then glazing and artwork. Banquettes against a wall before anything passes in front of them.
Then a levelling pass with the tables in place, because chair height is checked against the table.
Two suppliers a day is the working maximum for an unfamiliar crew. The crew that has installed this furniture before works 30% faster, which is worth paying for.
Install sequence sits in the setup guide, and the punch-list week in punch list week.