Installation Labour: How Many People for 200 Chairs

Two people can install 200 chairs in a day if the cartons are sorted by room. Four people take two days if they are not.

Part of the lead time guide — Where the 25 to 35 Days Actually Go

The rate

Finished chairs: 40–50 per person per day including unpacking, positioning and waste removal. Tables: 15–20 per person per day, because levelling takes time.

So 200 chairs and 40 tables is four people for two days, with a fifth for waste and floor protection.

What slows it down

Cartons sorted by model instead of room. Lifts out of service. Floors not finished so furniture has to move twice. Missing glides, which stops a whole row.

Each of those is a planning failure, not a labour shortage.

Sequencing

Fixed seating first, then tables, then chairs, then glazing and artwork. Banquettes against a wall before anything passes in front of them.

Then a levelling pass with the tables in place, because chair height is checked against the table.

The crew

Two suppliers a day is the working maximum for an unfamiliar crew. The crew that has installed this furniture before works 30% faster, which is worth paying for.

Install sequence sits in the setup guide, and the punch-list week in punch list week.

Where this applies