Reading a Production Report: Four Numbers That Tell the Truth

Progress reports say 'on schedule' until the day they do not. Four numbers turn the sentence into evidence.

Part of the lead time guide — Where the 25 to 35 Days Actually Go

The four numbers

Frames completed, frames upholstered, chairs packed, cartons labelled. Four counts against the order quantity, updated weekly with photographs.

Anything else is commentary. The report with those four numbers can be checked in a minute.

What a healthy report looks like

Linear progress against the plan, not a jump in the last week. Photographs showing the actual batch, not a stock image of the model.

And a stated next-week target. The report without a forecast has no information in it.

Red flags

Frames at 100% and upholstery at 0% for three weeks means the cover is late. Packing at 60% and labelling at 10% means cartons are short.

Either one is visible three weeks before it becomes a delivery delay, which is the point of asking.

How to ask for it

Weekly, on a fixed day, one page, with four photos. Written into the order confirmation. The supplier who reports without being asked is a supplier worth keeping.

Material status sits in deposit timing and material release, and inspection in pre-shipment inspection.

Where this applies

More from the workshop

Have a room to fit out?

Send the floor plan and the seat count. Quote and finish chip in one reply.

Start a conversation →