The container arrives, the site is not ready, and the port charges per day. Free time is a number on the booking that decides the cost.
Demurrage is charged on the container inside the terminal. Detention is charged on the container outside it. Free time is the days allowed before either starts.
Typical free time is 5–7 days at destination, and container detention runs 7–14 days from collection.
Rates vary by port and carrier, and they escalate. The week past free time on a 40HQ can cost more than the ocean freight.
On a hotel project with a delayed handover, that is a real budget line.
Clear customs before arrival and book the delivery slot before the vessel lands. Then unload into a warehouse within free time even if the site is not ready.
Warehouse storage is cheaper than demurrage, and the cartons stay dry.
Depends on the Incoterm. Under CIF or CFR the buyer pays from arrival. Under DAP the seller pays to the named place. Under DDP the seller pays everything.
Incoterm detail sits in Incoterms for furniture buyers, and port delays in shipping schedule and port congestion.