Six hundred chairs in three deliveries sounds efficient. It usually means three setups, three freight bookings and three colour batches.
Each delivery has its own carton run, its own container booking and its own inspection. Setup cost per delivery is roughly fixed, so three shipments of 200 cost more per chair than one of 600.
Then the batch problem: three coating batches, three cover rolls, three kiln charges. Colour matching across three deliveries is harder than across one.
Floor-by-floor opening, where rooms come online over months. Refurbishment in a live hotel, where the room stock cannot all be out at once. Cash flow, where a single payment for 600 chairs is not possible.
Each of those is a real constraint. Phasing for storage reasons is not — that is what a warehouse is for.
Make all the frames in one run, and hold the later deliveries at the factory or in a local warehouse. That keeps one timber batch and one coating batch, and turns phasing into a logistics question rather than a production one.
If the frames must be made separately, keep the cover rolls from one dye lot and record the roll numbers per delivery. Roll numbers recorded per order and matched on re-cover.
Delivery schedule with dates, storage terms and who pays for storage beyond 30 days. Then a colour continuity clause: all deliveries from the same timber and coating batch where possible.
Freight and packing sequencing sit in the lead time guide, and cover continuity in cover matching across batches.