Kiln Capacity: The Bottleneck Nobody Asks About

A factory can machine 500 chairs a week and dry timber for 300. The kiln is the real capacity figure.

Part of the factory guide — Inside a Chair Workshop in Lecong

Why drying is slow

Green timber at 60% moisture goes to 8–10% at packing over three to four weeks in a kiln, depending on species and thickness. There is no way to rush it without cracking the timber.

So kiln volume per charge, multiplied by charges per month, is the ceiling on monthly output.

What to ask

Kiln capacity in cubic metres, number of chambers, and the schedule for the species you are buying. Then: how much of that capacity is already committed.

The factory that buys dried timber instead of drying it has no kiln constraint and a higher material cost. Both are legitimate; only one is usually disclosed.

Why it matters for the order

If the order lands when the kiln is full, the timber waits. That wait does not appear in a 25-day production quote, because the quote assumes dry stock on the rack.

Which is why the honest question is not lead time but stock: is the timber for this order dry and on site?

Checks on the timber

Ask to see the moisture record for the charge that will be used. Then check a cut face with a meter yourself at packing.

Moisture targets sit in the chair timber guide, and packing checks in QC stations and checks.