Thirty per cent deposit, seventy on shipment is the norm. The question is what protects the seventy.
30% deposit on order, 70% against the bill of lading. On larger orders, 30/40/30 with the middle payment on pre-shipment inspection.
The deposit covers materials — timber and cover are bought before production starts, and a supplier funding 200 chairs alone is a supplier who will ask for more later.
Inspection before the balance, not after. Pre-shipment inspection report with photographs, dated, issued before payment. That is the only leverage a buyer has once goods are on the water.
Then documents against payment: bill of lading released on receipt. Standard, and it works as long as the inspection happened first.
5–10% held for 30 days after delivery is normal on fit-out contracts and rare on furniture orders. Where a project has a snagging process, retention is reasonable and a supplier will price it in.
Ask for it explicitly rather than deducting it later. Deductions after the fact damage the spares relationship, which is the thing you need in year four.
Full payment in advance, however good the discount. Payment against a photograph of a container. And any structure where the inspection report and the payment are handled by the same person.
Inspection sequencing sits in pre-shipment inspection, and contract terms in the specifying guide.
Send the floor plan and the seat count. Quote and finish chip in one reply.
Start a conversation →