24 Nov 2026·Lead Time
Site Readiness: Nine Things That Must Be True
Furniture arriving into a wet building is furniture stored in a humid room. Site readiness is a condition of delivery, not a courtesy.
24 Nov 2026·Lead Time
Installation Labour: How Many People for 200 Chairs
Two people can install 200 chairs in a day if the cartons are sorted by room. Four people take two days if they are not.
24 Nov 2026·Lead Time
Cartons, Foam and Pallets: The Waste Nobody Budgets
Two hundred chairs arrive in 200 cartons with foam, plastic and pallets. Getting that off site is a cost line, not a detail.
24 Nov 2026·Lead Time
The Punch-List Week: What Gets Fixed and What Gets Deferred
Forty items on the list, five days before opening. Sorting them by what guests see is the only way through.
24 Nov 2026·Lead Time
Seasonal Capacity in Foshan: The Year in Four Quarters
Everything is possible in June and nothing is possible in December. The workshop calendar decides more dates than the quotation does.
24 Nov 2026·Lead Time
Reading a Production Report: Four Numbers That Tell the Truth
Progress reports say 'on schedule' until the day they do not. Four numbers turn the sentence into evidence.
24 Nov 2026·Lead Time
Air Freight: When It Is Cheaper Than Waiting
Air freight costs eight to twelve times sea. It still pays for itself on parts, samples and any delay that would move an opening date.
24 Nov 2026·Lead Time
Free Time, Demurrage and the Bill Nobody Expects
The container arrives, the site is not ready, and the port charges per day. Free time is a number on the booking that decides the cost.
24 Nov 2026·Factory
What a Furniture Factory Audit Actually Checks
Most audits score a building. The useful ones score four processes, and two of them are about paperwork rather than machines.
24 Nov 2026·Factory
How to Spend Four Hours in a Factory
A factory visit is a sequence, not a tour. Start where the timber comes in and finish where the cartons leave.
24 Nov 2026·Factory
Workshop Layout: Why Flow Decides Quality
Parts that travel twice get damaged twice. Layout is the cheapest quality control a factory has.
24 Nov 2026·Factory
Machining Tolerances in Timber: What Is Achievable
Wood moves with the weather. The tolerance written for steel is a tolerance nobody can hold in a chair factory.